
wonders what boiling this time round.
got an announcement of dissolution to e subsidiary yesterday...
Look like warming up now ???.
 
raymaster ( Date: 07-Aug-2013 15:14) Posted:
|
no sound no picture.
fishy counter, beware might sudden engine power up late.
good luck.
 
Very encouraging results will bring the confidents of the Investors back.....Cheers!
happyharvest ( Date: 03-Aug-2013 22:16) Posted:
|
happyharvest ( Date: 03-Aug-2013 22:16) Posted:
|
Peter_Pan ( Date: 03-Aug-2013 12:11) Posted:
|
Gindalbie Metals says its half-owned Karara project has produced its first premium-grade concentrate, but the magnetite mine could need millions more from China's Ansteel before it is fully operational.
Managing director Tim Netscher said yesterday Karara had produced its first 68 per cent magnetite concentrate. But commissioning delays had forced Karara to again push back a deadline for sustainable production at its target 8 million tonne a year production rate, which will now not occur for at least another two months.
Karara costs an estimated $60 million a month to run. It will almost certainly need to call on Ansteel for additional support before it becomes cash-flow positive.
Mr Netscher would not be drawn on how much extra cash would be needed to carry Karara through to full production, saying the vagaries of the ramp-up process and difficulties in predicting iron ore prices made it impossible to judge Karara's revenue over coming months.
"It's difficult to speculate on any shortfall," he said. "But Ansteel is committed to funding that shortfall, which will be in the form of project loans, which in due course will get converted to bank loans."
Delays have already forced its owners to inject more than $200 million in working capital so far this year, the bulk in loans from Ansteel.
In June, Gindalbie gave up the right to buy out loans extended to Karara on its behalf by Ansteel and allowed the Chinese steelmaker the right to move to majority ownership of the project by converting some of its debt to equity.
Karara is also fighting with a number of its contractors. That includes a $55 million claim from Singapore-listed AusGroup, which claimed in the Supreme Court in June that Karara had been withholding payments since March.
Mr Netscher said Karara was still in dispute with about four other contractors but said the figures involved were "significantly lower" than the AusGroup claim.
"We've finished a $3.2 billion project," he said.
"We have as a result of that - and this is quite normal - about 10 different disputes going with different contractors. About half of those are resolved already - perhaps one will wind up getting resolved in court, the others I'm confident will get resolved out of court.
"There's nothing abnormal in that. We've perhaps taken a slightly harder line than others would take - we have insisted on getting performance and where it hasn't happened we've raised a dispute."
Will this latest announcement bring a rebound to Ausgroup's shares? Will shortists run to cover? 5 Aug 2013, zhun zhun 1 month after this analyst's report, trading begins on a new note!
Peter_Pan ( Date: 05-Jul-2013 16:39) Posted:
|
 
The Supreme Court of Western Australia has today ordered AGC and KML to submit the dispute on a confidential basis to a Court supervised mediation. This follows the recent receipt of a progress payment against an outstanding invoice for AU$13 million and the return of a bank guarantee in the amount of AU$10.9 million. Notwithstanding the legal action, both AGC and KML continue to work through outstanding issues.
AusGroup Managing Director and CEO Laurie Barlow said: " AGC is pleased that KML has agreed to make payment on an outstanding invoice and believe that a successful outcome is achievable."
 
The Company will make the necessary announcements when there are any material updates on the above matter
Octavia ( Date: 12-Jul-2013 10:11) Posted:
|